(Prepared Fall 2004)
Background
Wake County Board of Commissioners unanimously adopted the
Wake County Water/Sewer Plan in September 1998. The plan represented
the culmination of an effort that had been initiated in July
1997. During that effort, Wake County worked with key stakeholder
groups and the county’s 12 municipal governments to
build consensus on the logical and orderly expansion of water
and sewer service to serve the county.
The Western Wake [Cape Fear River basin] Regional Water Reclamation
Facility is a key recommendation of the Wake County Water/Sewer
Plan. Because wastewater treatment capacity is an important
issue to several local governments in western Wake County,
time has been of the essence to move this project toward implementation.
In May 2002, Apex, Cary, Fuquay-Varina, Holly Springs, Morrisville,
and Wake County formally agreed to jointly commission the
Western Wake County Regional Wastewater Treatment Studies
project. While the municipal governments agreed to work cooperatively
on the study effort, no local government was bound or required
to continue their participation beyond the study effort.
The Western Wake County Regional Wastewater Treatment Studies
project addressed:
• The need for additional capacity to serve growing
areas in Wake County.
• The required return of treated wastewater to the
Cape Fear Basin by Jan. 1, 2011 according to the terms of
the interbasin transfer certificate issued by the N.C. Environmental
Management Commission to Apex, Cary, Morrisville and Wake
County (for Research Triangle Park South).
• An expressed preference by state regulatory agencies
for regional wastewater management planning.
• The schedule for bringing facilities online. (The
amount of time between an optimistic permitting, design, and
construction schedule and the time when most of the participating
municipal governments would reach capacity is about the same.
Some local governments will exceed the capacity of their existing
wastewater treatment facilities before 2011.)
The purpose of the study was to enable the towns to evaluate
the technical, financial, regulatory, and environmental impact
factors associated with various options to address wastewater
capacity needs to the year 2030.
Project Work Plan
The management and coordination for the study was provided
by a technical management team consisting of a senior staff
person from each of the participating municipal governments
and Wake County. The county manager and town managers or their
designees provided oversight. The goals of the two phases
of study were to provide the project partners with the information
to select the most efficient and effective solution that meets
regional needs.
Phase I Study (November 2002 – September 2003)
This phase focused on identifying and evaluating alternative
wastewater management options and the development of a reclaimed
water program. The project partners initially reviewed 24
wastewater management options and selected seven options for
more detailed evaluation.
The criteria for detailed evaluation of the seven
options were:
• Present worth costs for capital, operations and maintenance
• Direct environmental effects
• Institutional complexity
• Reclaimed water potential
• Effect on water supply safe yield
• Project schedule uncertainty
Recommendation – Four options were selected
for further review in Phase I. The towns agreed to pursue
a series of Phase III studies to obtain approval for whatever
option was selected.
Phase II Study (October 2003 – July 2004)
This phase focused on the financial impacts and alternative
organizational models for four wastewater management options.
The four options selected for the Phase II study (Options
1, 5, 9, and 10D) scored most favorably during the evaluation.
Option 1 represents the “baseline” option of
each municipal government acting independently to address
wastewater capacity needs. The other three options represent
varying degrees of cooperation. The Phase II work plan included:
• Development of a more refined implementation schedule
• Evaluation of the financial resources required for
implementation
• Evaluation of alternative organizational models for
intergovernmental cooperation to implement the preferred wastewater
management solution
• Selection of a preferred wastewater management solution
Recommendation – Option 10D selected was the
preferred wastewater management solution.
Phase III Study
N.C. Department of Environment and Natural Resources representatives
have said an environmental impact statement (EIS) will be
needed because of the size and complexity of the proposed
project and the anticipated degree of public interest. The
purpose will be to identify the environmental impacts and
define measures to mitigate them.
Phase III studies include:
Conducting Preliminary Site Investigations
The towns initially reviewed 29 possible water reclamation
sites. They selected 12 sites for more detailed evaluation.
The evaluation included parcel information for selected sites
and adjacent sites, property tax information, river and stream
buffer data, land use data, topography, aerial photography,
soils data, and wetland mapping data.
The results of the additional evaluation yielded three possible
sites for a new water reclamation facility. For planning purposes,
one site (Site 14) was selected to develop facility cost estimates
for raw wastewater pumping and conveyance, wastewater treatment,
sludge management and disposal, and effluent discharge to
the Cape Fear River.
Pursuing Jordan Lake Discharge
During the Phase I study, the towns studied discharge to
Jordan Lake as well as to the Cape Fear River. They saw benefits
from discharging to Jordan Lake. The study also indicated
that the potential savings in pumping and conveyance facilities
for a Jordan Lake discharge versus a Cape Fear River discharge
were on the order of $15 million to $20 million.
In light of the identified benefits and potential savings,
the towns commissioned a detailed study to pursue a discharge
to Jordan Lake. During this part of the study, it was determined
that the N.C. Department of Environment and Natural Resources
has been working to address point and non-point sources of
total nitrogen and total phosphorous for the entire lake.
Environment and Natural Resources has determined that a maximum
daily load for nitrogen and total phosphorous is necessary
because parts of Jordan Lake are an impaired water body based
on the chlorophyll a standard. With a total daily maximum
load soon to be established, it would be necessary for the
towns to purchase total nitrogen and total phosphorous capacity
(in pounds per year) from one or more of the existing Jordan
Lake dischargers in order to secure a new National Pollutant
Discharge Elimination System permit.
Because the costs associated with purchasing total phosphorous
and total nitrogen capacity as well as the potential delay
associated with additional water quality sampling and modeling,
the towns decided to pursue a new discharge to the main stem
of the Cape Fear River.
Conducting Dwarf Wedgemussel Surveys
From meetings with the Department of Environment and Natural
Resources during the Phase I study, the towns learned it would
be necessary to conduct dwarf wedgemussel surveys, a federally
listed endangered species. Those surveys would be for the
Wake County portions of the Swift and Middle Creek drainage
basins that are within the utility service areas of Apex,
Cary, Morrisville, and Holly Springs. The purpose was to assess
distribution and numbers of dwarf wedgemussels within those
service areas and to develop secondary and cumulative impact
mitigation plans.
The towns met with representatives of NC DENR and the U.S.
Fish and Wildlife Service in May and June 2004 to prepare
the mussel survey plan. Surveys were conducted at 40 sites,
which included approximately 5,145 meters (2.93 miles) of
stream in June and July 2004.
Of the 40 sites surveyed, 21 were in the Middle Creek sub-basin
and 19 were located in the Swift Creek sub-basin. State and
federal representatives participated in field survey activities.
During the survey, no live or relic specimens of dwarf wedgemussels
were found. The draft Mussel Survey Report was submitted in
August 2004.
Preparing Secondary and Cumulative Impact Mitigation
Plan Documents
Secondary and cumulative impacts are those that are indirectly
caused or facilitated by a proposed project. They typically
occur during the 20- or 30-year period after construction
of the proposed facilities. These impacts are typically associated
with the development that occurs in the service area(s) for
a proposed project.
Mitigation of secondary impacts is frequently required. The
mitigation may include ordinances already in place and other
measures that a municipal government would implement to minimize
the environmental impacts. For the Phase III studies, the
towns have elected to develop mitigation plans that can be
used to address planned infrastructure projects within each
municipal government’s service area for five to seven
years.
Alternative Intergovernmental Cooperation Options
The results of the evaluation of alternative organizational
models have been documented for the Project Partners in the
form of a technical memorandum titled, “Technical Memorandum
6.0 – Organizational Models for Intergovernmental Cooperation.”.
Recommendations
Since each currently operates efficient and effective water
and sewer delivery organizations, the towns determined that
the most efficient and effective organization for regional
wastewater management facilities would be the interlocal agreement
model using the joint agency approach.
Features of the recommended organizational model
include:
• Reduced unit cost of service for capital facilities,
operations, and maintenance.
• Improved quality and reliability of service.
• Local decision-making for level-of-service requirements.
• Local decision-making for establishing rates, fees,
charges.
• Cooperative decision-making for facility staffing,
operations, and maintenance.
• Cooperative decision-making for capital improvement
planning and implementation.
• Cooperative decision-making for annual budget preparation.
• No redundant government services.
Preferred Wastewater Management Solution
Generally, each of the four options selected for additional
study in Phase II (Option 1, 5, 9 and 10D) were equal in level
and quality of service, regulatory review and approval requirements,
and technical complexity. The group agreed that a modification
of Option 10D was the preferred wastewater management solution.
Option 10D Modification
To improve the level of service provided by Option 10D, the
towns included Holly Springs. Holly Springs determined there
was a cost advantage to keeping its Utley Creek plant and
discharging treated wastewater to the outfall serving the
regional plant. In July 2004, state officials confirmed they
would work with the towns on that proposal.
Under the modified Option 10D, regional facilities would
provide wastewater treatment for Apex, Cary, Morrisville,
and the Wake County portion of Research Triangle Park (RTP
South). Holly Springs would continue using its Utley Creek
plant and discharge up to 4 million gallons a day to an outfall
serving the Western Wake regional plant and the Utley Creek
plant. The line would discharge treated effluent to the Cape
Fear River downstream of Buckhorn Dam.
Fuquay-Varina will not participate in the use, financing,
or construction of regional facilities. Fuquay-Varina will
meet its needs with its Terrible Creek Wastewater Treatment
Plant and Harnett County’s North Harnett Regional Wastewater
Treatment Plant.
Program Management
In June 2004, the towns agreed that the best approach would
be the interlocal agreement model. The first interlocal agreement
will address land acquisition, NPDES permitting, and EIS/201
Facilities Plan preparation. The second interlocal agreement
will address final design, construction, ownership, operations,
maintenance, and management of the facilities.
The towns assigned Cary to be the lead agency. A technical
advisory committee will have senior staff members from each
participating town. The Town of Cary Public Works and Utilities
director will chair the committee.
Program Requirements
Under the proposed implementation plan, each town will continue
to own, operate, and maintain its facilities. Each town will
be responsible for its water and sewer billing, revenue collection,
management, administration and customer service.
Each town will be responsible for constructing facilities
to deliver wastewater to the regional raw wastewater pumping
stations.
The technical advisory committee’s regional project
work will cover land acquisition, permits, design and construction,
and facility staffing, operations and maintenance.
Program Costs
Estimated costs for the first phase of the modified Option
10D are estimated at $199 million.
The Grants and Loans staff of the N.C. Division of Water
Quality has indicated that low-interest loan funding is available
through the Clean Water State Revolving Fund program. The
staff said that approximately $5 million for permitting and
design and $60 million for construction is available. To receive
the money, a 201 Facilities Plan is required.
Funding Sources
Each municipal government may use water and sewer enterprise
funds for its pro-rata share of the costs. They will likely
be required to adjust rates, fees and charges to generate
enough money for the regional project. Some combination of
the following funding sources is likely for land acquisition,
permitting, design, and construction:
• Pay-as-you-go
• State Revolving Fund (low-interest loan)
• General obligation bonds
• Revenue bonds
As the lead agency, Cary will be responsible for providing
timely and accurate budget forecasts to each municipal government
for administration, operations and maintenance.
|